Tuesday, June 27, 2006

Let's be realistic ...

So ... now that all of you who have actually laid hardwood before have had a good laugh at the progress we expected to make during our first attempt at installation, we'll revise our goals to more closely model reality.

What actually happened on the weekend was we got almost 2 sides of the hallway (our hallway is shaped like a U) done, we painted the front wall in the hallway, and burned some scrap lumber.

So ... our new schedule looks like:

Tuesday: Peter - finish laying hardwood on first two sides of hallway along with a few rows into the office and guest room. Angela - teach a friend how to lay tile.

Wednesday: Worship team practice. Possibly lay some hardwood once we get home.

Thursday: Lay hardwood in guest room.

Friday: Lay hardwood in office (finish guest room first if not completed).

Saturday: Hang door in master bath. Lay hardwood in office. Lay remaining tile in master bath and laundry room (just a few tile - maybe 10 total).

Monday (yay - holiday!): Grout tiles laid on Saturday and tub surround. Lay hardwood on third side of hallway.

Hopefully this schedule is reasonable. I'll let you know ;)

No comments: