Tuesday, March 14, 2006

Weekly plan

It's that time again - time to figure out our "schedule" for the next week. We've seen lots of progress in the last week, so it's pretty easy to stay motivated right now! We need to capitalize on that ;)

Our short-term goal is to have the house ready for the plumber by March 25th. Here is the list of what's left to finish for that goal:
  1. Paint half-bath ceiling
  2. Paint half-bath walls (2 coats)
  3. Lay floor in half-bath
  4. Grout floor in half-bath
  5. Finish crack-filling master bath
  6. Joint and plane boards for master bath vanity face frame
  7. Attach face frame to master bath vanity
  8. Stain vanity (2 coats)
  9. Varathane vanity (2 coats)
  10. Prime master bath
  11. Paint ceiling in master bath
  12. Paint walls in master bath (may only need 1 coat as it's white over white primer)
  13. Install master bath vanity
Whew! Alright, so our first steps will be ...

Tuesday:
  • Lay tile in half-bath
  • Crack-fill master bath
  • Plane boards for face frame
Wednesday:
  • Plane boards for face frame
    Thursday:
    • Lay rest of tile in half-bath

    Friday:
    • Paint half-bath (ceiling and walls)
    • Put together face frame
    • Attach face frame to vanity
    • Stain vanity (coat 1)
    Saturday:
    • Paint half-bath walls
    • Prep and grout floor in half-bath
    • Crack-fill master bath
    • Stain vanity (coat 2)
    I think that should put us on a good course for finishing on time. We shall see how closely we stick to that schedule!

    And, as you can see, I'm starting to customize some links and trackers at right. It's about time!

    No comments: